Do exercises 1.51-1.53 from pages 49-50. (You will need to refer to
page 48.)
-
From the data on page 73, how much higher is the CPI of the 200 MHz
Pentium system than the CPI of the 100 MHz Pentium system on the
SPECint95 workload? On the SPECfp95 workload? (Ignore the issue that
each SPEC ratio is actually a geometric mean over different programs;
pretend that a single int workload and a single fp workload is represented.)
-
Do exercises 2.31-2.32 on page 96.
-
You are the manager of a microprocessor design team. Your
microprocessor currently has an average CPI of 1.5. The software that
will run on your microprocessor already exists and is fixed: it will
not be rewritten or recompiled in response to your design decisions.
One of the members of your design team suggests a change that will
reduce the CPI of multiply instructions from 3 to 2 (and leave the CPI
of other instructions unchanged). However, it will require
lengthening the cycle time by 5%. You need to decide whether this
change is desirable or not.
-
In order to make this decision, you need to ask the software experts
for one specific numerical piece of information about the software
that will be run on the microprocessor. What is this one number that
is key to your decision? (Remember: it is to be a fact about the
software itself, not about how the software will run on the hardware.)
-
How large does that number need to be for the design change to be a
good idea? (This assumes that a larger number is more favorable for
the design change. If the reverse is true, state how small the number
needs to be for the design change to be a good idea.)